SKYPLAZA COMMERCIAL DEVELOPMENT
Hong Kong INTERNATIONAL AIRPORT

Developer - HK Airport Authority
Architect - Aedas SOM Joint Venture
Engineers - Ove Arup & Partners HK
Contractor - Chun Wo - Fujita JV

Our Clients - Leighton Hsin Chong JV
Tender Stage, April to May 2004

 
     

 


JUNE 2004

Site Mobilisation. The figures quoted are the production rates for each month

Pile Caps – 54 No
Sheet Piling – 1000 sq m
Temp Works Steel – 30 t
Excavation – 2100 m3
Concrete – 1500 m3

 
     

 


JULY 2004

The pile caps were intended to be constructed from the east side working towards the west. This was the planned sequencing for all the works.

Pile Caps – 114 No
Column Pours – 48 No
Slab Pours – 2 No
Excavation – 20,000 m3
Concrete – 3,500 m3

 
     

 

AUGUST 2004

The ground floor slab was not on the critical path. The contractor planned two areas of construction for the superstructure - North & South and the sections worked towards each other from the East.

Pile Caps – 42 No
Column Pours – 80 No
Slab Pours – 8 No
Excavation – 19,000 m3
Concrete – 9,000 m3

 
     

 

SEPTEMBER 2004

By month four, all of the ground works are completed and the slabs on Level 6 have commenced. The extension of the APM tunnels in the centre of the site are also nearly completed.

Column Pours – 80 No
Slab Pours – 16 No
Excavation – 6,000 m3
Concrete – 13,000 m3

 
     

 

OCTOBER 2004

The rate of concrete pouring was planned to be at the peak at this stage with large areas of the ground floor and suspended slabs completed.

Column Pours – 80 No
Slab Pours – 23 No
Concrete – 14,000 m3

 
     

 

NOVEMBER 2004

The concreting works are nearly completed in all the key areas. The superstructure for the North Office has also commenced.

Column Pours – 80 No
Slab Pours – 21 No
Concrete – 12,000 m3

 
     

 

DECEMBER 2004

The new departures road and base slab for the new bus interchange are completed. The protective deck will commence on the east perimeter of Level 6 to allow the facade installation commence.

Column Pours – 45 No
Slab Pours – 18 No
Concrete – 9,500 m3

 
     

 

January 2005

The primary steel for the 36mx36m 2 way spanning roof trusses commences. the contractor planned to erect the steel by using tower cranes on moving bogies.

Column Pours – 20 No
Slab Pours – 7 No
Concrete – 4,000 m3
Roof Truss Erection – 330 t

 

 
     

 

FEBruary 2005

As the roof steelwork is completed in large areas, the roof sheeting commences. The acoustic roof panels were planned to be erected in pre-fabricated panels. The main facade installation has also commenced in two areas.

Roof Truss Erection – 570 t
Roof Sheeting @ 650 m2 /day
Cladding @ 250 m2 /day

 

 
     

 

MARCH 2005

The steelwork is nearly complete and the North Office building structure is nearing completion.

Roof Truss Erection – 570 t
Concrete – 2,000 m3
Roof Sheeting @ 650 m2 /day
Cladding @ 250 m2 /day

 
     

 

APRIL 2005

The roof sheeting and facade is completed. The building is water tight and the M&E and architectural fitout commences

 

 

MAY 2005

The building was planed to be completed within 12 months.

 
 